Work that has not yet been invoiced

Invoicing Outstanding Payments - By Month

Total unpaid work will be invoiced in 4 separate segments, corresponding approximately to the work done in the preceding period.

Oct 06: 100 hrs @ $50 blended rate = $5,000
Dec 06: 100 hrs @ $50 blended rate = $5,000
Jan 07: 100 hrs @ $50 blended rate = $5,000
Mar 07: 102 hrs @ $50 blended rate = $5,100


Total outstanding invoices as of 5/15/2007 = $20,100

College Prep 2007 - Application Phase

Week of

Person

Hours

Dec 4 - Dec 8

India Team

14 hours

Dec 11 - Dec 16

India Team

11 hours

Dec 18 - Dec 22

 

 

Dec 27 - Dec 30

India Team

3 hours

Jan 02 - Jan 05

DGG

3 hours

Jan 02 - Jan 05

India Team

3 hours

Jan 08 - Jan 12

DGG

3 hours

Jan 15 - Jan 21

DGG

11 hours

Jan 15 - Jan 21

India Team

4 hours

Jan 22 - Jan 28

DGG

19 hours

Jan 22 - Jan 25

India Team

30 hours

Jan 29 - Feb 04

DGG

15 hours

Jan 29 - Feb 03

India Team

30 hours

Feb 05 - Feb 11

DGG

12 hours

Feb 05 - Feb 09

India Team

10 hours

Feb 13 - Feb 18

Lobo

4 hours

Feb 12 - Feb 18

DGG

12 hours

Feb 12 - Feb 18

DGG

4 hours

Feb 12 - Feb 17

India Team

30 hours

Feb 19 - Feb 23

India Team

18 hours

Feb 26 - Mar 2

DGG

3 hours

Feb 26 - Mar 2

Lobo

3 hours


Total for CPS 07: 242 hrs.

Load Testing and CiviCRM Optimization

Dec 11 - Dec 15: 1 x 20 = 20 hours
Dec 18 - Dec 22: 1 x 20 = 20 hours
Dec 27 - Dec 29:
Jan 02 - Jan 05: 1 x 10 = 10 hours
Jan 08 - Jan 12: 1 x 10 = 10 hours


Total for Optimization = 60 hrs.

College Match Processing Phase

Sep 25 - 29: 1 x 20 hours = 20
Oct 02 - 06: 2 x 20 hours = 40
Oct 09 - 13: 1 x 20 hours = 20
Oct 16 - 20: 2 x 10 hours = 20


Total for this phase = 100 hrs.

Work that has been invoiced and paid

College Match Launch Phase

July 10 - 14: 5 x 30 hours = 150
July 17 - 21: 5 x 30 hours = 150
July 24 - 28: 5 x 30 hours = 150
July 31 - Aug 4: 5 x 30 hours = 150
Aug 7 - 11: 5 x 30 hours = 150
Aug 14 - 18: 5 x 20 = 100


Total for this phase = 850 hrs.

Preapplication Phase

Nov - Mar 10: Dave / Lobo combined spent approx 100 hours on Branner including meetings, product specs, review etc

Mar 13 - Mar 17: 60 hours (dave + lobo) + 60 hours (india team)

Mar 20 - Mar 24: 60 hours (dave + lobo) + 60 hours (india team)

Mar 27 - Mar 31: 60 hours (dave + lobo) + 100 hours (india team)

Apr 3 - Apr 7: 60 hours (dave + lobo) + 60 hours (india team)

Apr 9 - Apr 14: 50 hours (dave + lobo) + 60 hours (india team)

Current Total (till Apr 14): 390 hours (US) + 340 hours (IN)