Work that has not yet been invoiced
Invoicing Outstanding Payments - By Month
Total unpaid work will be invoiced in 4 separate segments, corresponding approximately to the work done in the preceding period.
Oct 06: 100 hrs @ $50 blended rate = $5,000
Dec 06: 100 hrs @ $50 blended rate = $5,000
Jan 07: 100 hrs @ $50 blended rate = $5,000
Mar 07: 102 hrs @ $50 blended rate = $5,100
Total outstanding invoices as of 5/15/2007 = $20,100
College Prep 2007 - Application Phase
Week of |
Person |
Hours |
|---|---|---|
Dec 4 - Dec 8 |
India Team |
14 hours |
Dec 11 - Dec 16 |
India Team |
11 hours |
Dec 18 - Dec 22 |
|
|
Dec 27 - Dec 30 |
India Team |
3 hours |
Jan 02 - Jan 05 |
DGG |
3 hours |
Jan 02 - Jan 05 |
India Team |
3 hours |
Jan 08 - Jan 12 |
DGG |
3 hours |
Jan 15 - Jan 21 |
DGG |
11 hours |
Jan 15 - Jan 21 |
India Team |
4 hours |
Jan 22 - Jan 28 |
DGG |
19 hours |
Jan 22 - Jan 25 |
India Team |
30 hours |
Jan 29 - Feb 04 |
DGG |
15 hours |
Jan 29 - Feb 03 |
India Team |
30 hours |
Feb 05 - Feb 11 |
DGG |
12 hours |
Feb 05 - Feb 09 |
India Team |
10 hours |
Feb 13 - Feb 18 |
Lobo |
4 hours |
Feb 12 - Feb 18 |
DGG |
12 hours |
Feb 12 - Feb 18 |
DGG |
4 hours |
Feb 12 - Feb 17 |
India Team |
30 hours |
Feb 19 - Feb 23 |
India Team |
18 hours |
Feb 26 - Mar 2 |
DGG |
3 hours |
Feb 26 - Mar 2 |
Lobo |
3 hours |
Total for CPS 07: 242 hrs.
Load Testing and CiviCRM Optimization
Dec 11 - Dec 15: 1 x 20 = 20 hours
Dec 18 - Dec 22: 1 x 20 = 20 hours
Dec 27 - Dec 29:
Jan 02 - Jan 05: 1 x 10 = 10 hours
Jan 08 - Jan 12: 1 x 10 = 10 hours
Total for Optimization = 60 hrs.
College Match Processing Phase
Sep 25 - 29: 1 x 20 hours = 20
Oct 02 - 06: 2 x 20 hours = 40
Oct 09 - 13: 1 x 20 hours = 20
Oct 16 - 20: 2 x 10 hours = 20
Total for this phase = 100 hrs.
Work that has been invoiced and paid
College Match Launch Phase
July 10 - 14: 5 x 30 hours = 150
July 17 - 21: 5 x 30 hours = 150
July 24 - 28: 5 x 30 hours = 150
July 31 - Aug 4: 5 x 30 hours = 150
Aug 7 - 11: 5 x 30 hours = 150
Aug 14 - 18: 5 x 20 = 100
Total for this phase = 850 hrs.
Preapplication Phase
Nov - Mar 10: Dave / Lobo combined spent approx 100 hours on Branner including meetings, product specs, review etc
Mar 13 - Mar 17: 60 hours (dave + lobo) + 60 hours (india team)
Mar 20 - Mar 24: 60 hours (dave + lobo) + 60 hours (india team)
Mar 27 - Mar 31: 60 hours (dave + lobo) + 100 hours (india team)
Apr 3 - Apr 7: 60 hours (dave + lobo) + 60 hours (india team)
Apr 9 - Apr 14: 50 hours (dave + lobo) + 60 hours (india team)
Current Total (till Apr 14): 390 hours (US) + 340 hours (IN)