College Prep Scholarship 07 Timeline
Task |
Responsible |
Start Date |
End Date |
|---|---|---|---|
|
|
|
|
Servers ready for load testing |
Quest |
11/26/06 |
12/12/06 |
Load Testing |
CiviCRM |
12/13/06 |
1/23/07 |
CPS Specs |
Quest |
11/17/06 |
1/10/06 |
Reader Specs |
Quest |
1/2/07 |
1/17/07 |
CPS Development |
CiviCRM |
1/11/07 |
2/02/07 |
CPS Testing |
Quest |
2/05/07 |
2/09/07 |
Bug Fixes |
Quest & CiviCRM |
2/12/07 |
2/16/07 |
Load Testing |
CiviCRM |
2/19/07 |
2/23/07 |
CPS 07 Launch |
Quest & CiviCRM |
03/01/07 |
03/01/07 |
Reader UI Development |
CiviCRM |
2/01/07 |
2/28/07 |
Reader Flow Testing and Fixes |
Quest & CiviCRM |
3/01/07 |
3/15/07 |
Last day for App Submit |
Quest |
|
3/31/07 |
Reader Review and Winner Selection |
Quest |
4/01/07 |
4/15/07 |